It appears that the right to grant an extension of time (“EOT“) can be implied into a contract, as was decided by the High Court in Era Kemuncak Jaya (M) Sdn Bhd v Tenaga Switchgear Sdn Bhd [2021] 1 LNS 1570. Continue reading “IMPLIED RIGHT TO GRANT EOT”
Tag: EOT
CONCURRENT DELAY & REASONABLE TIME
Concurrent delay is usually considered in the context of extension of time (“EOT”) to complete construction works. In RC Asia Engineering Sdn Bhd v Lion Pacific Sdn Bhd [2021] 1 LNS 1667 however, the High Court had occasion to consider concurrent delay – or overlapping delay – in the assessment of reasonable time to complete such works. Continue reading “CONCURRENT DELAY & REASONABLE TIME”